Construction Update 3/25/2019

The electrical and plumbing shutdown scheduled for Tuesday, March 19 went very smoothly. The work was completed successfully and the building re-opened three hours sooner than expected. If there are any problems remaining in any …

Construction Update 3/18/2019

Partial shutdown of electrical power systems in the chemistry complex – now confirmed for Tues Mar 19th from 2:00 am until 12:00 noon. New information regarding expanded scope of work:  in addition to the power shutdown, the UW …