Construction Update 08/26/2019

Chemistry Learning Center. We are happy to report that bids are in for the new facilities of the Chemistry Learning Center (CLC). The general contractor will be Advanced Building Corporation. Their bid was very slightly …

Construction Update 08/12/2019

New Tower.  Progress was modest during the past week.  The major accomplishment involved work in the sub-basement of the Daniels building.  Construction of the rooms that will contain the electrical sub-station for the new tower …