Construction Update 08/12/2019
New Tower. Progress was modest during the past week. The major accomplishment involved work in the sub-basement of the Daniels building. Construction of the rooms that will contain the electrical sub-station for the new tower …
Construction Update 08/05/2019 – Loading Dock Closure 8/7
New Tower. The main activity of the past week was the preparation for a day-long session (4:30 am – 4:30 pm) of pouring concrete on Wed July 31st. The first major section to be poured …
Department welcomes Ryan Stowe, Assistant Professor
On August 1, 2019 chemist and education researcher Ryan L. Stowe, joins the Department of Chemistry. Stowe received his B.A. in chemistry from Albion College (2010) in Michigan and his Ph.D. in chemistry from The …
Notice 7/31/2019: Loading Dock Closure
The closure of the chemistry loading dock, originally scheduled for 4:00am – 10:30am on Wed July 31st, has been rescheduled for 4:15am – 11:00am on Thurs Aug 1st. – Bob McMahon
Construction Update 07/23/2019
New Tower. During the past two weeks concrete has been poured in the sub-basement level for some of the columns that will hold the weight of the nine floors above. Concrete has also been poured …
Department welcomes Jeff Martell, Assistant Professor
Jeff Martell arrived at UW-Madison May 20, from a postdoctoral researcher position with Jeff Long at UC Berkeley’s Miller Institute. His group currently includes two first-year Ph.D. students, Edward Pimentel and Mario Cribari. Martell received …
Construction Update 07/08/2019
New Tower. Because of the holiday, last week was a three-day work week, so there is less to report than usual. Work continues in the sub-basement and on the trusses that were installed last week …
Construction Update 07/01/2019
New Tower. A second set of trusses, each weighing about 73,500 pounds, has been successfully installed. These trusses span the 250-seat lecture room and will support the weight of eight stories of the northeast corner …