Construction Update 5/13/2019

Tower excavation—lots happening!  Concrete has been poured for many of the footings and some of the walls for our new tower. Last week concrete footings were poured in the bottom of the pit for the …

Construction Update 5/6/2019

Tower Crane. Success! The tower, turntable, and cab of our tower crane were erected over the weekend. Friday night equipment was brought in and lanes were closed on University Avenue. Early Saturday morning the construction team …