Construction Update 07/01/2019

New Tower.  A second set of trusses, each weighing about 73,500 pounds, has been successfully installed. These trusses span the 250-seat lecture room and will support the weight of eight stories of the northeast corner …

Construction Update 06/03/2019

New Tower. Most of the excitement this week involved installation of two 50-ton trusses and several cross members on the steel columns that were erected several weeks ago. This process began with preparation of gravel …

Construction Update 5/13/2019

Tower excavation—lots happening!  Concrete has been poured for many of the footings and some of the walls for our new tower. Last week concrete footings were poured in the bottom of the pit for the …

Construction Update 5/6/2019

Tower Crane. Success! The tower, turntable, and cab of our tower crane were erected over the weekend. Friday night equipment was brought in and lanes were closed on University Avenue. Early Saturday morning the construction team …