New Tower. The tower is now rising above ground level and preparations are being made for pouring concrete for the part of the second floor that will become the new information commons (library). Much shoring …
Building Updates
Notice 10/23/2019: Loading Dock Closure 10/29-10/30
The driveway to the chemistry loading dock will be inaccessible on Tue Oct 29th and Wed Oct 30th. Construction crews will be using a conveyor system to back-fill around the foundation walls on the west …
Notice 10/23/2019: Driveway Inaccessible 10/29-10/30
The driveway to the chemistry loading dock will be inaccessible on Tue Oct 29th and Wed Oct 30th. Construction crews will be using a conveyer system to back-fill around the foundation walls on the west …
Construction Update 10/21/2019
New Tower. There was a lot of activity in the new tower last week. We now have additional concrete floors and extensions of concrete columns above the basement and first-floor levels, concrete walls up …
Construction Update 10/14/2019
New Tower. The big news last week was the largest concrete pour of the project—almost 11 hours long. Last Thursday, from 4 am to about 3 pm a concrete pump truck in the loading-dock area …
Construction Update 10/07/2019
New Tower. The new tower area looks completely different from what you saw in the last newsletter. Shoring and concrete forms now cover much of the basement and first-floor areas in preparation for pouring concrete …
Construction Update 09/30/2019
New Tower. A lot has been accomplished in the excavation during the past two weeks. (There was no newsletter September 16, so this report covers two weeks.) Concrete was poured Thursday afternoon and evening in …
Construction Update 09/16/2019
Daniels Sub-basement. The new rooms in the Daniels sub-basement that will house a new emergency generator and other electrical equipment were finished some weeks ago. Last week workers were installing conduit ducts that will carry …
Construction Update 09/08/2019
New Tower. Erection of rebar and concrete forms for walls of the east (Mills Street side) stairwell and the elevator shafts continued last week. After the bases of these walls are poured, waterproofing will be …
Construction Update 09/03/2019
New Tower. Last week concrete was finally poured for what will be part of the basement floor in the tower. After being postponed from the week before, scheduled for Tuesday, rescheduled for Wednesday, and re-rescheduled, …